Extend the Sowers Middle School rebuild schedule and cover extra contractor costs
IN SHORT
Goal: The rebuild is completed by about May 1, 2025. (plus 1 more goal below)
Result: Partly met. Public documents show part of the goal was met, or a result smaller than first estimated.
The Sowers Middle School rebuild, awarded in January 2022 with a contract value of $49,704,502 (including a 5% contingency), ran into 181 days of delays from weather, utility work, soil conditions, and other issues. The board approved a $429,751 change order, paid from the project's contingency, and the district set a new expected completion date.
Brief
Receipt
Stamp (current stage)
01
Brief
What the board was deciding. Budget words explained
- Meeting
- January 14, 2025, agenda item 12.4
- Vote
- Approved
- Ayes: 5
- Noes: 0
- Abstain: not recorded
- Absent: not recorded
- Cost or savings
- $429,751 taken from the project's contingency to cover 92 days of the contractor's extended overhead. The district said this amount is included within the final guaranteed maximum price.
- Options considered
- No alternatives were listed in the documents reviewed.
- Who is affected
- Sowers Middle School students, families, and staff: The rebuilt campus's completion date moved from the initial November 1, 2024 to an anticipated May 1, 2025.Source(opens in a new tab)
02
Receipt
What the district said, word for word.
GOAL 01
“The new completion date for the project is anticipated to be May 1, 2025.”
Agenda item 12.4, Background · Signed Board Minutes, January 14, 2025 (item 12.4), p. 9(opens in a new tab)
- In plain words
- The rebuild is completed by about May 1, 2025.
- Estimated amount
- No dollar amount stated
GOAL 02
“The project is still anticipated to return contingency once complete.”
Agenda item 12.4, Background · Signed Board Minutes, January 14, 2025 (item 12.4), p. 9(opens in a new tab)
- In plain words
- The project finishes under its contract value, so unused contingency goes back to the district.
- Estimated amount
- No dollar amount stated
REVIEW DATE
May 1, 2025()
Review date set by the district.
“The new completion date for the project is anticipated to be May 1, 2025.” Source, p. 9(opens in a new tab)
03
Timeline
What happened, in order.
Board awards the Sowers rebuild construction contract to Construct 1 One Corporation
Board vote: Approved 5–0
Review due (date set by district)
Contractor completes its work, with a final project cost of $49,683,159
Board accepts the work and files a Notice of Completion
Stamped: Partly met
- TODAY
04
Stamp
How did it turn out? What the stamps mean
Stamps describe what public documents show. They are never a judgment of anyone's work or intentions.
Stamped October 5, 2026 · Every quote checked against its source · Approved by a person before publishing
Cost: met. The district reported a final project cost of $49,683,159, which is $21,343 below the $49,704,502 contract value that included the contingency, so some contingency was left unspent, as the district anticipated. Schedule: about a month later than anticipated. The district reported the contractor completed its work as of May 31, 2025, compared with the anticipated May 1, 2025. The board accepted the work and filed a Notice of Completion on September 9, 2025.
Evidence
How this was decided
- Goal checked
- “The new completion date for the project is anticipated to be May 1, 2025.”“The project is still anticipated to return contingency once complete.”
- Review date
- May 1, 2025 (review date set by the district)
- Rule applied
- "Partly met" means: Public documents show part of the goal was met, or a result smaller than first estimated. The five stamps
- What was found
- The explanation above, based on 2 documents listed under Evidence.
- Reviewed
- Every quote checked against its source; approved by a person on October 5, 2026.
District response
Not yet invitedWhen the district is invited to review this record, the date will appear here, and any response will be added in the district's own words.
New stamps: the district gets 10 business days to review a stamp before it's published. How district responses work
05
Sources
Every document used on this page.
- 1.Board Agenda, January 14, 2025 (item 12.4) (opens in a new tab)
- 2.Signed Board Minutes, January 14, 2025 (consent calendar) (opens in a new tab) · pages 5, 8, 9
- 3.Signed Board Minutes, September 9, 2025 (item 12.7, Notice of Completion) (opens in a new tab) · pages 3, 12
- 4.Board Agenda Packet, January 18, 2022 (Sowers rebuild lease-leaseback contracts) (opens in a new tab) · page 112
Record last updated October 5, 2026. See something wrong? Send a correction.
Share this decision
Print it for a board packet or public comment, or paste the card below into a newsletter or website.
Cite as: Receipts. "Extend the Sowers Middle School rebuild schedule and cover extra contractor costs." Huntington Beach City School District decision record, last updated October 5, 2026. https://districtreceipts.netlify.app/decisions/2025-01-14-sowers-rebuild-schedule-change/
More facilities decisions
- LED lighting retrofit projectReview Not yet due
Follow this decision
Get an email if this record is updated, for example when the district shares a response. Nothing else.
Opens Buttondown in a new tab to confirm. Unsubscribe anytime.